Sheet Pile Infills

Sheet Pile Infills are designed as a quick, economical and lightweight solution to infilling the open pans in an exposed sheet pile wall.

Features

Aids the extraction of the sheet piles following construction of the concrete retaining wall.
Provides a flat profile for the installation of construction membranes or an in-situ concrete wall.
Removes the need for backfilling in a confined space.
Lightweight and easy to handle.
Each infill unit is accurately cut on a CNC machine to suit the exact profile of the sheet pile system; typically supplied in 1.2 metre lengths.

Applications

For the infilling of the open pans within a sheet piling wall design installation to aid removal following construction of the associated concrete retaining wall. It provides a flat profile for the installation of a waterproof membrane.

This article comes from cordek edit released

Installation of Steel Sheet Piling

Procedure and Equipment

According to Recommendations of the Committee for Waterfront Structures Harbours and Waterways EAU 1996, “Steel sheet piling is frequently an ideal solution both as regards structural considerations and driving conditions, which is also capable of absorbing localized overloading without endangering overall stability.” (Section 8.1.3.1, page 280).

The installation of a combined sheet piling wall system is typically a two- or three-step process:

  1. Use a vibro hammer to drive the beams or king piles as far as possible.
  2. Use an impact hammer to drive the beams to the designed toe depth (if necessary).
  3. Set the intermediate sheet piling (with attached connector) between the king piles.

Recommendations of the Committee for Waterfront Structures Harbours and Waterways EAU 1996 also notes that, “The embedment depth of the intermediate piles for high harbour walls in good bearing soil should be at least 2.5 m; for low walls with slight water pressure difference, it should be at least 1.5 m.” (Section 8.2.10.4, page 355).

Strengthening the Wall for Hard Driving Conditions

A toe adjustment can be made at the mill (for an additional fee) or by the contractor on site:

20160113

A note on driving, and the advantages of driving a combined sheet piling wall:

The fact that you only need to drive the beams to full depth and then simply set the intermediate sheets is an extremely important advantage of the combined sheet piling wall over heavier sheet piling from contiguous walls.

Driving Experiences and Practical Tips

A traditional combined sheet piling system has a typical sheet width of 6.33 feet (1.93 M) – two halves of each beam, two connectors, and two intermediate sheets. The usual sheet-to-beam ratio in a combined sheet piling wall system is around 75% sheet to 25% beam. Hence, you are likely to only encounter hard driving 25% of the length of a combined sheet piling wall system versus 100% hard driving for a contiguous sheet pile wall. In some cases where hard driving was experienced, it has been documented that up to 22 combined sheet piling wall sections have been driven in one 10-hour shift, amounting to well over 100 wall feet; in the same conditions, however, the same exact crew was only able to install about 1/3 of the wall feet with the heavy contiguous sheet piling that needed to be driven to full depth.

Another advantage of driving hot rolled combined sheet piling over traditional contiguous walls (such as with cold formed sheets) is addressed in the U.S. Army Corps of Engineers’ 1994 Sheet Piling Design Manuals for Engineers. Cold-rolled sections have a weaker interlock than the hot-rolled sections and in hard driving conditions this interlock might “unzip” or cause alignment problems which would require replacement of the sheet piles. The cold-rolled sections also are usually thin and may be prone to overstressing during driving” (Section 8-8a).

(This article comes from iSheetPile editor released)